Back to Insights
Case Study

Building-to-IDC Transformation: Challenges and Opportunities

Building-to-IDC Transformation: Challenges and Opportunities


Introduction

With the rapid development of the AI industry, data center demand has surged. Building new IDCs takes time and is costly, making the transformation of existing buildings into AI-ready data centers a new trend. This article shares our experience and insights from actual transformation projects.

Project Background

Transformation Target: A commercial office building in Taipei (B2-4F)
Original Use: Traditional office space
Transformation Goal: Support 1,000 GPU AI training center
Project Timeline: 6 months (2024/04-2024/09)
Total Investment: NT$350 million

I. Preliminary Assessment

1.1 Building Structure

Load-bearing Capacity Testing

  • Original design load: 500 kg/m²
  • AI server requirements: 800-1,200 kg/m²
  • Solution: Reinforce floor structure, distribute load

Ceiling Height

  • Original floor height: 3.6m
  • Required clear height: 2.8m (including cable trays)
  • Conclusion: Meets requirements, no additional treatment needed

1.2 Power System

Existing Capacity

  • Building total capacity: 2,000 kVA
  • Available for IDC: 1,500 kVA (excluding public facilities)

Demand Analysis

  • GPU power consumption: 700W × 1,000 = 700 kW
  • CPU/Network/Storage: 200 kW
  • Cooling system: 300 kW
  • Total Demand: 1,200 kW + 20% margin = 1,440 kW

Transformation Plan

  • New dedicated transformers (2 × 1,000 kVA)
  • Dual feed A+B power supply
  • N+1 UPS configuration (500kVA × 3 units)

1.3 Cooling System

Original System

  • Traditional central air conditioning
  • Cooling capacity: 500 RT (refrigeration tons)

AI Workload Requirements

  • Heat dissipation: 1,200 kW ≈ 340 RT
  • Problem: Existing system insufficient capacity and low efficiency

Transformation Plan

Cooling Tower (Roof)
    ↓
Chiller Units (400 RT × 2 units, N+1)
    ↓  
Chilled Water Circulation System
    ↓
In-row Air Conditioners (CRAC) in Data Hall

Key Design

  • Hot/Cold Aisle Containment
  • Raised floor air supply
  • Reserved liquid cooling upgrade interface

II. Construction Phase

2.1 Month 1: Demolition and Foundation Work

  • Remove existing partitions and ceilings
  • Floor reinforcement work
  • Power wiring pre-installation

Challenge: Building still operational on other floors, requiring phased construction

2.2 Months 2-3: MEP System Installation

M (Mechanical)

  • Chiller installation
  • Pipeline configuration
  • Air conditioning units positioning

E (Electrical)

  • Transformer installation
  • Distribution panel layout
  • UPS system configuration
  • Monitoring system wiring

P (Plumbing)

  • Fire sprinkler system
  • Leak detection system

2.3 Month 4: Data Hall Finishing

  • Raised floor installation (600mm height)
  • Cable tray installation
  • Access control system configuration
  • Environmental monitoring sensor deployment

2.4 Month 5: Equipment Installation

  • 42U standard racks (120 units)
  • InfiniBand switches
  • Server rack mounting
  • Network cabling

2.5 Month 6: Testing and Acceptance

  • Power system testing
  • Cooling system commissioning
  • Network connectivity testing
  • GPU burn-in testing
  • Fire drill

III. Technical Challenges and Solutions

3.1 Floor Load-bearing

Problem: B2 floor insufficient load capacity

Solution:

  • Add support columns
  • Optimize rack layout to distribute weight
  • Use lightweight racks (aluminum alloy)

3.2 Heat Exhaust

Problem: Limited roof space, difficult cooling tower installation

Solution:

  • Use high-efficiency compact cooling towers
  • Phased deployment, install capacity for 500 GPU first
  • Reserve space for second-phase expansion

3.3 Network Cabling

Problem: Insufficient conduit space in existing building

Solution:

  • Use vertical cable trays
  • Some routes along exterior walls
  • Use high-density fiber (MPO/MTP)

3.4 Noise Control

Problem: Office building sensitive to noise

Solution:

  • Double-layer soundproof doors for data hall
  • Sound absorption treatment in equipment rooms
  • Silencers added to cooling towers

IV. Cost Analysis

| Item | Amount (NT$10K) | Percentage | |------|----------------|------------| | Power System | 8,000 | 23% | | Cooling System | 10,000 | 29% | | Building Finishing | 5,000 | 14% | | IT Equipment | 10,000 | 29% | | Other (Fire/Monitoring) | 2,000 | 6% | | Total | 35,000 | 100% |

Investment Recovery

  • Rack rental: NT$150K/month per rack
  • Total racks: 120 units
  • Target occupancy: 80%
  • Monthly revenue: NT$14.4M
  • Payback Period: Approximately 2.5 years

V. Operational Data (After 3 Months)

Power Efficiency

  • PUE: 1.35 (target <1.4)
  • Electricity cost: Approximately NT$6M per month

Cooling Efficiency

  • Supply water temperature: 12°C
  • Return water temperature: 18°C
  • Data hall temperature: 24±2°C

Availability

  • Uptime: 99.95%
  • Planned maintenance: Once per month
  • Unplanned outages: 0

VI. Experience Summary

Success Factors

  1. Thorough Preliminary Investigation: Spent 2 months on detailed assessment
  2. Flexible Design: Reserved 30% expansion capacity
  3. Professional Team: Cross-disciplinary collaboration of IDC + Building + MEP
  4. Phased Deployment: 50% capacity first, reducing risk

Points to Note

  1. Regulatory Approval: Building use change took 2 months
  2. Neighbor Coordination: Construction noise required prior communication
  3. Supply Chain: Long lead-time equipment like UPS needed early ordering
  4. Testing Time: Don't compress acceptance testing cycle

VII. Future Planning

Short-term (Within 6 months)

  • Achieve 80% occupancy
  • Attract more AI customers

Medium-term (Within 1 year)

  • Second-phase expansion (+500 GPU)
  • Introduce liquid cooling technology
  • Upgrade to GB200 systems

Long-term (2+ years)

  • Replicate experience in other buildings
  • Establish Building-to-IDC transformation service brand

Conclusion

Transforming traditional buildings into AI data centers is a viable and economical path. The key lies in:

  • Solid preliminary assessment
  • Professional design and construction
  • Reasonable cost control
  • Long-term operational planning

We are happy to share more experience and assist building owners and investors interested in entering this field.


Contact Us
If you are interested in building-to-IDC transformation projects, please contact:
Email: building@huisuanlabs.com
Tel: +886-2-XXXX-XXXX

Share this article